Re: After reconstruction
Author: Howard
Date: 10-19-2014 - 16:49
Espee99 Wrote:
-------------------------------------------------------
> Howard, is the the only bridge being completely
> replaced, and if so will service start to the
> potential customers once it is completed?
>
> Thanks for the continuing updates.
The burnt timber trestle at milepost 23.54 will be replaced with a culvert and fill. The timber trestles at mileposts 4.87 and 11.16 will be repaired. I would imagine delivers to the customer at the Cliffside location (Thompson Street yard) could start anytime after the bridge work completes.