October. Conflicts with VIP scheduling required it. The project itself, although moving slow, is actually not that far behind schedule. What delays they are having are arising from unforeseen complexities in operating the line, and from a delay in equipment delivery by CRC. First DMU will not be on the property until June, and the remaining cars not until August.

Signals are currently scheduled for cut in on June 1, with testing beginning then, regardless of if there is a DMU on property.

The maintenance facility is pretty much done, though they're still playing with some exterior track arrangements, including a fenced pen around a storage track.



Subject Written By Date/Time (PST)
  Westside Express Service Construction Tom McCann 03-19-2008 - 18:55
  Re: Westside Express Service Construction wigwagfan 03-20-2008 - 20:42
  Re: Westside Express Service Construction Jerry Loy 03-22-2008 - 03:55
  Re: Westside Express Service Construction Arlen Sheldrake 03-22-2008 - 17:22
  Re: Westside Express Service Construction FHL 03-22-2008 - 19:00


Go to: Message ListSearch
Subject: 
Your Name: 
Spam prevention:
Please, enter the code that you see below in the input field. This is for blocking bots that try to post this form automatically.
 ********  ********   ******   **      **  ******** 
    **     **        **    **  **  **  **     **    
    **     **        **        **  **  **     **    
    **     ******    **        **  **  **     **    
    **     **        **        **  **  **     **    
    **     **        **    **  **  **  **     **    
    **     ********   ******    ***  ***      **    
This message board is maintained by:Altamont Press
You can send us an email at altamontpress1@gmail.com