Re: Metrolink's Late Trains - PTC startup was a factor
Author: Max Wyss
Date: 02-03-2016 - 13:57

ETCS Level 2 uses GSM-R for communication, and Balises (aka track beacons) for updating the exact position of the vehicle (and being on the particular track, there is no confusion about on which track the train operates). It does not rely on GPS for positioning.

GSM-R may eventually become obsolete and replaced with some kind of LTE-R.



Subject Written By Date/Time (PST)
  Metrolink's Late Trains - PTC startup was a factor mook 02-01-2016 - 11:00
  Re: Metrolink's Late Trains - PTC startup was a factor Speeder Kevin 02-01-2016 - 17:50
  Re: Metrolink's Late Trains - PTC startup was a factor Max Wyss 02-02-2016 - 01:15
  Re: Metrolink's Late Trains - PTC startup was a factor Speeder Kevin 02-03-2016 - 09:52
  Re: Metrolink's Late Trains - PTC startup was a factor BOB2 02-03-2016 - 11:03
  Re: Metrolink's Late Trains - PTC startup was a factor Max Wyss 02-03-2016 - 13:57


Go to: Message ListSearch
Subject: 
Your Name: 
Spam prevention:
Please, enter the code that you see below in the input field. This is for blocking bots that try to post this form automatically.
 **    **  **     **  ********   **      **   ******   
  **  **   **     **  **     **  **  **  **  **    **  
   ****    **     **  **     **  **  **  **  **        
    **     **     **  **     **  **  **  **  **   **** 
    **      **   **   **     **  **  **  **  **    **  
    **       ** **    **     **  **  **  **  **    **  
    **        ***     ********    ***  ***    ******   
This message board is maintained by:Altamont Press
You can send us an email at altamontpress1@gmail.com