Re: Good News For The SC&MB And The Polar Express.
Author: Howard
Date: 12-09-2016 - 04:09
JDM Wrote:
-------------------------------------------------------
> Howard they found defects which did not meet FRA
> class one track, again not notifying the FRA was
> not a minor clerical error and the defects should
> not have been in the track in the 1st place it is
> not that hard to maintain track to FRA class I and
> yet IPH failed to do that they had defects which
> they needed to repair now the eyes of the FRA will
> be on them more often so they better keep the
> track up.
I said the lack of notification was the reason for the 10 day shut down. I do not consider that minor.