Tutor Perini installs 3.2 miles of substandard rails in SF job ...
Author: Graham Buxton
Date: 05-11-2018 - 21:11

Quote:
SF Chronicle
The opening of Muni’s Central Subway from Caltrain to Chinatown is already a year behind schedule, but it could be pushed into 2020 after the discovery that a contractor installed 3.2 miles of the wrong grade of rail.

In an April 19 letter, the Municipal Transportation Agency told contractor Tutor Perini that it would reject the rails as not meeting the specifications of the contract, and called for them to be removed and replaced with high-strength rails at the contractor’s expense. That cost is unknown.

As first reported in the San Francisco Examiner, an independent auditor discovered the problem. The project calls for the use of high-strength steel rail for the $1.6 billion subway, but Tutor Perini and a subcontractor, Con-Quest Contractors, installed standard-strength rails, the MTA said.

Read the rest here:
https://www.sfchronicle.com/bayarea/article/SF-subway-stalled-after-contractor-lays-down-12905429.php

Note that Tutor Perini is also milking the California HSR project for every dollar it possibly can. Here is an interesting article from last year: [californiapolicycenter.org]



Subject Written By Date/Time (PST)
  Tutor Perini installs 3.2 miles of substandard rails in SF job ... Graham Buxton 05-11-2018 - 21:11
  Re: Tutor Perini installs 3.2 miles of substandard rails in SF job ... Carol L Voss 05-11-2018 - 22:47
  Re: Tutor Perini installs 3.2 miles of substandard rails in SF job ... synonymouse 05-11-2018 - 22:51
  Re: Tutor Perini installs 3.2 miles of substandard rails in SF job ... Commenter 05-12-2018 - 00:37
  Re: Tutor Perini installs 3.2 miles of substandard rails in SF job ... Bill Hough 05-12-2018 - 10:15
  Re: Tutor Perini installs 3.2 miles of substandard rails in SF job >> clickable link Graham Buxton 05-12-2018 - 05:06
  Re: Tutor Perini installs 3.2 miles of substandard rails in SF job >> clickable link Anthony G. 05-12-2018 - 07:08
  Re: Tutor Perini installs 3.2 miles of substandard rails in SF job >> clickable link BOB2 05-12-2018 - 07:37
  Re: Tutor Perini installs 3.2 miles of substandard rails in SF job >> clickable link George Andrews 05-12-2018 - 08:40
  Re: Tutor Perini installs 3.2 miles of substandard rails in SF job >> clickable link david vartanoff 05-12-2018 - 09:39
  Re: Tutor Perini installs 3.2 miles of substandard rails in SF job >> clickable link SP5103 05-12-2018 - 10:51
  Re: Tutor Perini installs 3.2 miles of substandard rails in SF job >> clickable link Nussel Snouts 05-12-2018 - 12:40
  Re: Tutor Perini installs 3.2 miles of substandard rails in SF job >> clickable link BOB2 05-12-2018 - 15:01
  Re: Tutor Perini installs 3.2 miles of substandard rails in SF job ... Ed Workman 05-12-2018 - 17:02
  Re: Tutor Perini installs 3.2 miles of substandard rails in SF job ... HUTCH 7.62 05-12-2018 - 17:45
  Re: Tutor Perini installs 3.2 miles of substandard rails in SF job ... Commenter 05-12-2018 - 19:09
  Re: Tutor Perini installs 3.2 miles of substandard rails in SF job ... BOB2 05-12-2018 - 20:24
  Re: Tutor Perini installs 3.2 miles of substandard rails in SF job ... Carol L Voss 05-12-2018 - 20:36


Go to: Message ListSearch
Subject: 
Your Name: 
Spam prevention:
Please, enter the code that you see below in the input field. This is for blocking bots that try to post this form automatically.
  ******   **      **  **     **  ********    ******   
 **    **  **  **  **  ***   ***  **     **  **    **  
 **        **  **  **  **** ****  **     **  **        
 **        **  **  **  ** *** **  **     **  **   **** 
 **        **  **  **  **     **  **     **  **    **  
 **    **  **  **  **  **     **  **     **  **    **  
  ******    ***  ***   **     **  ********    ******   
This message board is maintained by:Altamont Press
You can send us an email at altamontpress1@gmail.com