KGO-TVTuesday, September 25, 2018 11:14PM
SAN FRANCISCO (KGO) -- The Salesforce Transit Center in San Francisco is temporarily closed after crews discovered a fissure in a steel beam on the third level of the center Tuesday, officials announced.
The Transbay Joint Powers Authority emptied the Salesforce Transit Center Tuesday evening after workers discovered a crack in a load-bearing beam.
Commuters trying to catch the bus were floored to learn the new $2 billion transit center has a defect.
"The Millennium Tower, now this. I'm sure there has to be some issues going on with the construction people," said bus commuter Sid Goel.
"Well the beam is cracked so the behavior of the beam is unpredictable and that's why our engineers are cautious and they want us to close that area," said Executive Director of the TJPA, Mark Zabaneh.
Zabaneh adds that the cracked beam is in the ceiling of the third level bus deck on the eastern side of the transit center near Fremont Street. The horizontal beam is beneath the rooftop park.
Zabaneh says the crack was discovered around 10 a.m. Tuesday morning while workers were installing ceiling panels.
"It's very disappointing for us responsible for building the transit center, and it's very disappointing that we have to inconvenience the public," he added.
More here:
[
abc7news.com]