Re: Castro-station-elevator-project-delayed-until-fall-2021
Author: Bean Counter
Date: 11-26-2020 - 17:13

Jesus! 15 million seems a little steep for an elevator. Why so expensive?



Subject Written By Date/Time (PST)
  Muni Metro elevator work delayed synonymouse 11-26-2020 - 10:49
  Castro-station-elevator-project-delayed-until-fall-2021 Actual Title 11-26-2020 - 11:41
  Re: Castro-station-elevator-project-delayed-until-fall-2021 Bean Counter 11-26-2020 - 17:13
  Re: Castro-station-elevator-project-delayed-until-fall-2021 SFMTA SUCKS 11-27-2020 - 20:09