Current standard:

For the air brakes: Brake pipe, main reservoir equalizing, independent application and release, actuating (bail)

For the electrical: 27 pin connection for

Negative
Control
Engine Run (old fuel pump)
Headlight mu
Throttle solenoid control (x4)
Generator Field
Alarm
Sand
Emergency Sand
Dynamic brakes (x4)
Air Compressor Synchronization
Forward
Reverse
Depending on the options or age of the loco, the others might be used for boiler control and blowdown, switching service, transition, hump control, Fuel Saver, etc.



Subject Written By Date/Time (PST)
  MU cables Jim G. 03-16-2021 - 08:16
  Re: MU cables JIm G. 03-16-2021 - 08:19
  Re: MU cables J 03-16-2021 - 08:28
  Re: MU cables Hot Water 03-16-2021 - 08:26
  Re: MU cables Jim G. 03-16-2021 - 11:32
  Re: MU cables J 03-16-2021 - 17:41
  Re: MU cables SP5103 03-17-2021 - 13:02
  Re: MU cables kalebking79 03-17-2021 - 02:01
  Re: MU cables / Bluetooth J 03-17-2021 - 07:28
  Re: MU cables Dr Zarkoff 03-17-2021 - 13:19


Go to: Message ListSearch
Subject: 
Your Name: 
Spam prevention:
Please, enter the code that you see below in the input field. This is for blocking bots that try to post this form automatically.
 ********  **    **  ********   **     **   ******  
    **     ***   **  **     **  **     **  **    ** 
    **     ****  **  **     **  **     **  **       
    **     ** ** **  ********   **     **  **       
    **     **  ****  **         **     **  **       
    **     **   ***  **         **     **  **    ** 
    **     **    **  **          *******    ******  
This message board is maintained by:Altamont Press
You can send us an email at altamontpress1@gmail.com