St. Maries Benewah bridge
Author: hepkema
Date: 04-02-2007 - 10:04

First-hand info regarding the project:
Anticipated re-opening is April 26. To date, 49 bents have been repaired with new piles driven down up to 160'. Nine steel spans have been constructed to replace the worst section. What they discovered was that over the years, maintenance would be done from the closest (east) end to HQ. This work would work proceed west until the money or budget stopped. By the time they got back to it in a year or 2 or 3, some new work would be needed again in the east side before proceeding west. As a result, the west end got neglected.

I won't go into specifics regarding cost so far, but let's just say that if they had the $5.5 million in-hand that has been estimated to replace the bridge east of Colfax, they probably could have replaced the entire Benewah trestle.



Subject Written By Date/Time (PST)
  St. Maries Benewah bridge hepkema 04-02-2007 - 10:04
  Re: St. Maries Benewah bridge ST2-K 04-02-2007 - 12:18
  Re: St. Maries Benewah bridge hepkema 04-02-2007 - 12:28
  Re: St. Maries Benewah bridge Frank 04-02-2007 - 14:00


Go to: Message ListSearch
Subject: 
Your Name: 
Spam prevention:
Please, enter the code that you see below in the input field. This is for blocking bots that try to post this form automatically.
 ********  **     **   *******   ********   *******  
    **     **     **  **     **     **     **     ** 
    **     **     **         **     **     **     ** 
    **     **     **   *******      **      ******** 
    **      **   **          **     **            ** 
    **       ** **    **     **     **     **     ** 
    **        ***      *******      **      *******  
This message board is maintained by:Altamont Press
You can send us an email at altamontpress1@gmail.com