Re: NWP / SMART any new news ON FRA punch list
Author: DAVE
Date: 02-07-2011 - 21:04
COPYED FROM BOARD PACK FOR WED MEETING NCRA
EO 21 FRA Inspection
FRA track and signal inspectors began the initial inspection of track and grade crossing
warning signals and bridge signals during the week of January 3-7, 2011. The track
inspection is complete. FRA’s signal inspectors returned to re-inspect selected signals
during the week of January 31 through February 3. By the end of the month, FRA
Region 7 will make a recommendation to FRA in Washington, DC regarding the lifting
of EO 21. FRA’s decision should come in late February or early March