Author: Divey
Date: 09-15-2011 - 15:23

Per the ACE people 'pipeline issues' are still holding up the work near Pomona.
I wouldn't expect to see serious DT work east of Guasti until the Milliken RR flyover is complete.

OTOH a few new box culverts between Pomona and Ontario would let them build seven miles of new main on the Alhambra sub. Short sidings on the Al side pretty much require eastbounds to go through Riverside.



Subject Written By Date/Time (PST)
  Double Tracking The Alhambra Sub Jim Speaker 09-14-2011 - 19:09
  Re: Double Tracking The Alhambra Sub Tree climber 09-14-2011 - 20:07
  Re: Double Tracking The Alhambra Sub Jim Speaker 09-14-2011 - 20:25
  Re: Double Tracking The Alhambra Sub Mr. Guy 09-14-2011 - 20:41
  Re: }Second Main" Track On The Alhambra Sub BOB2 09-14-2011 - 23:47
  Re: }Second Main" Track On The Alhambra Sub Conductor Jake 09-15-2011 - 10:51
  Re: }Second Main" Track On The Alhambra Sub BOB2 09-15-2011 - 12:51
  Re: }Second Main" Track On The Alhambra Sub Divey 09-15-2011 - 15:23


Go to: Message ListSearch
Subject: 
Your Name: 
Spam prevention:
Please, enter the code that you see below in the input field. This is for blocking bots that try to post this form automatically.
 ********  **     **  **      **  **    **  ********  
 **    **  **     **  **  **  **   **  **   **     ** 
     **    **     **  **  **  **    ****    **     ** 
    **     *********  **  **  **     **     ********  
   **      **     **  **  **  **     **     **     ** 
   **      **     **  **  **  **     **     **     ** 
   **      **     **   ***  ***      **     ********  
This message board is maintained by:Altamont Press
You can send us an email at altamontpress1@gmail.com