Then there ya go.
Graham Buxton Wrote:
-------------------------------------------------------
> Mistertower Wrote:
> --------------------------------------------------
> -----
> > Hey Mr. OPRRMS,
> > Any idea what they are doing? Is this anything
> to
> > do with the Suisun Bay Bridge, or is this just
> > major track work, both, or do you even know?
> > Thanks in advance, my inquiring mind would like
> to
> > know.
>
> This service change will allow Union Pacific’s
> track crews to perform maintenance on the Benicia-
> Martinez Bridge. These upgrades will allow the
> Capitol Corridor and other trains to operate at
> maximum authorized speed throughout that area and
> avoid possible future delays due to the rail
> condition.
>
> *This bridge work is dependent upon clear, dry
> weather and may be rescheduled accordingly.
>
>
> [
www.amtrakcapitols.com]
> ry-15-2011-bus-bridge-between-the-suisunfairfield-
> and-martinez-train-stations/