Re: CAHSR update
Author: les
Date: 11-08-2019 - 17:17

"Project Development Schedule (to ROD) - Information through July 31, 2019"

See page 42

"Publish Final EIS & Obtain ROD"

Note date 2021

[www.hsr.ca.gov]



FUD Wrote:
-------------------------------------------------------
> ROD usually implies that funding has been
> identified to carry out the work starting in a few
> years from approval. That's almost certainly not
> going to be the case for CAHSR.
>
> There's precedent of a sort, though: FRA issued a
> ROD for Desert Xpress, then reneged on the loan
> needed to build it, which rendered the ROD kind of
> meaningless. Virgin has now bought the company and
> the project, and found another way to get the loan
> (or at least a large part of it) via Private
> Activity Bonds, and apparently plans to use the
> old ROD.



Subject Written By Date/Time (PST)
  CAHSR update Commenter 11-08-2019 - 12:37
  Re: CAHSR update HUTCH 7.62 11-08-2019 - 14:53
  Re: CAHSR update LES 11-08-2019 - 15:42
  Re: CAHSR update FUD 11-08-2019 - 16:38
  Re: CAHSR update les 11-08-2019 - 17:17
  Re: CAHSR update FUD 11-08-2019 - 22:45
  Re: CAHSR update les 11-08-2019 - 23:28
  Re: CAHSR update Commenter 11-09-2019 - 10:16
  Re: CAHSR update Commenter 11-09-2019 - 10:18
  Re: CAHSR update M. Harris 11-09-2019 - 11:05
  Re: CAHSR update synonymouse 11-09-2019 - 11:30
  Re: CAHSR update LES 11-09-2019 - 13:27
  Re: CAHSR update Commenter 11-09-2019 - 20:05


Go to: Message ListSearch
Subject: 
Your Name: 
Spam prevention:
Please enter the code that you see below in the input field.
 **    **   ******    ********  **     **  ********  
  **  **   **    **   **    **  ***   ***  **     ** 
   ****    **             **    **** ****  **     ** 
    **     **   ****     **     ** *** **  ********  
    **     **    **     **      **     **  **     ** 
    **     **    **     **      **     **  **     ** 
    **      ******      **      **     **  ********  
This message board is maintained by:
Altamont Press Publishing Company