Re: Would a parallel track work?
Author: fkrock
Date: 07-06-2015 - 07:10
BOB2 Wrote:
-------------------------------------------------------
> I asked earlier about the width of the ROW on the
> segments in question, because, one solution would
> be to lay an additional set of rails, parallel to
> the current set, or, if they need to be shifted,
> within the same ROW.....which would allow for
> operation of both...?
>
> In looking at the aerials, it seems that a
> parallel track might be a possible outcome, as
> well. I think that this option and the upgrade of
> the WP segment to accomplish the same purpose
> would both be within any scope I would write, to
> look at the capacity needs identified by ACE and
> UP.
>
A parallel track might be possible in some parts of Niles Canyon. SP had several passing sidings between Niles and Sunol. However in the narrow part of the canyon the right of way has been carved into the canyon walls above the creek so widening the ROW would be very expensive and require moving much dirt.