Re: Infrastructure Improvements - Alameda Corridor - East
Author: Hogger
Date: 08-07-2015 - 09:00
Project Status
The total cost of the Temple Avenue train diversion project is $92.1 million. The construction cost for the fourth track work is $25.8 million, which is being jointly funded by the ACE Construction Authority and UPRR. In addition to installing the track and signal equipment over the entire fourth track length at their expense, UPRR will contribute $7.9 million toward the project. Work commenced in Fall 2008
and was completed in Winter 2009.
Completed my A$$!!