NCRA Press Release on Settlement
Author: Mike Pechner
Date: 10-28-2008 - 11:21

Mitch Stogner, Executive Director Allan Hemphill, NCRA Chairman
ncra.mstogner@sbcglobal.net vinguru@comcast.net

NOVATO DROPS LAWSUIT

PRESS RELEASE - October 28, 2008 –Ukiah – The North Coast Railroad Authority (NCRA)
today announced that the city of Novato has agreed to drop the lawsuit it filed against the rail
authority last September. NCRA’s Cloverdale Chairman, Allan Hemphill, said the settlement
agreement, approved by the NCRA and the Novato City Council on Monday, enables NCRA to
immediately begin repairing bridges and trackbed along a 62 mile stretch of the Northwestern
Pacific (NWP) line from Lombard to Windsor.

“This settlement establishes an equitable balance between the region’s desire to restore train
service and Novato’s desire to minimize impacts,” said Hemphill.

Under the agreement, which must be ratified by Marin Superior Court Judge James R. Ritchie,
NCRA will be limited to the operation of 6 freight trains per week during daylight hours until
improvements to reduce noise and promote safety are complete.

Specifically, NCRA must install Federal Railroad Administration (FRA) – certified “Quiet
Zones” at 13 locations within Novato where public roads cross the tracks. The improvements to
the crossing gates and signage will permit trains to travel through the crossings without sounding
the train horn. Additionally, NCRA has agreed to install welded rail to further mitigate noise,
fencing to discourage trespassing, landscaping to minimize glare from train lights, and purchase
state–of-the-art locomotives to reduce greenhouse gas emissions.

“We want to be good neighbors, good corporate citizens, and work collaboratively with local
governments every step of the way,” said Hemphill.

Until the mitigations stipulated in the lawsuit settlement are complete, NCRA cannot increase the
level of service beyond 3 roundtrips per week. The cost of the mitigation measures is estimated
to be around $1 million. The settlement also requires NCRA to pay Novato’s legal costs of
$325,000.

NCRA plans to release its environmental report evaluating train operations from Willits to the
national rail interchange (Lombard) in early November. The report anticipates a maximum of 3
roundtrips per day by the second year of operations.

“With this Settlement, we will repair the first 62 miles, initiate limited service while the required
mitigation is underway, and hopefully reach the level of service called for in the EIR after Novato
certifies that the mitigation requirements have been satisfied,” Hemphill said.

Under the Settlement agreement, NCRA has until December 31, 2011 to complete the “Quiet
Zones”, fencing, and landscaping within the Novato City limits.

Hemphill said the NCRA hopes to complete repairs on the first 62 miles in 4-6 months and begin
limited freight service this spring.



Subject Written By Date/Time (PST)
  NCRA Press Release on Settlement Mike Pechner 10-28-2008 - 11:21
  Re: NCRA Press Release on Settlement Drew Jacksich 10-28-2008 - 15:24
  Re: NCRA Press Release on Settlement Alfred Doten 10-28-2008 - 17:01
  Re: Answer to Drews qujestion. Mike Pechner 10-28-2008 - 17:35
  Re: Answer to Drews qujestion. Drew Jacksich 10-28-2008 - 17:39
  Re: Answer to Drews question. Mike Pechner 10-28-2008 - 19:14
  Re: Answer to Drews question. Drew Jacksich 10-28-2008 - 21:01
  Re: Answer to Drews question. forgotten 10-28-2008 - 21:18
  Re: Answer to Drews question. WAF 10-29-2008 - 06:42
  Re: Answer to Drews question. Jerry Peters 10-29-2008 - 08:06
  Re: Answer to Drews question. DAVE L 10-29-2008 - 10:30
  Thanks Mike ! Caboverbob 10-29-2008 - 21:03
  Thanks Mike ! Caboverbob 10-29-2008 - 21:03
  Re: Thanks Mike ! P.Kepler 10-29-2008 - 22:03


Go to: Message ListSearch
Subject: 
Your Name: 
Spam prevention:
Please, enter the code that you see below in the input field. This is for blocking bots that try to post this form automatically.
 ********  **     **  ********   **        **     ** 
 **        ***   ***  **     **  **        **     ** 
 **        **** ****  **     **  **        **     ** 
 ******    ** *** **  ********   **        **     ** 
 **        **     **  **         **        **     ** 
 **        **     **  **         **        **     ** 
 ********  **     **  **         ********   *******  
This message board is maintained by:Altamont Press
You can send us an email at altamontpress1@gmail.com